Notice of traffic management, Ashow Road and Crewe Lane
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-02-17/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Stoneleigh
- Contractor
- BBV JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 17/07/2023
- Estimated End Date
- 18/08/2023
What we are doing
We need to carry out electricity cable diversion and permanent drainage works on both Ashow Road and Crewe Lane. We will be carrying out these works in two phases over five weeks from 17 July 2023 to 18 August 2023.
Phase 1: 17 July to 11 August 2023, there will be a full road closure of Crewe Lane from the junction of Ashow Road. During this road closure there will also be two-way traffic signals on Ashow Road. This will provide a safe working area for works in the carriageway of Crewe Lane.
Phase 2: 11 August to 18 August 2023, three-way temporary traffic lights at the Junction of Ashow Road and Crewe Lane to enable works to be undertaken safely in the verge on the south side of Ashow Road and Crewe Lane
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]