S. Lacamas Creek (3rd Ave.) Trailhead Improvements
|
Project Status:  |
Active since 10/02/2023 |
Planned Completion: |
12/31/2025
This project is in progress. Project scope, activities, and dollars may change.
|
Project Type:  |
Development |
  |
|
Funding Board:  |
Recreation and Conservation Funding Board
|
    Funding |
  |
|
    RCO Grant Status
|
  |
Total RCO Grant:
|
$500,000.00
|
|
Paid To Date:
|
$0.00
|
(0%)
|
Grant Balance:
|
$500,000.00
|
(100%)
|
|
    Links |
  |
|
|
The City of Camas will use this grant to renovate the Lacamas Creek Trailhead located in the southern portion of Lacamas Lake Regional Park in Clark County. The City will install a new ADA restroom, utilities, ADA accessible pathways, picnic areas, signs, and site furnishings including picnic tables, benches, bike racks, trash receptacle, and dog waste stations. The City will also pave the parking area and improve landscaping and stormwater drainage. The primary recreation opportunities provided through this grant are passive recreation and nonmotorized use.
|
County:
|
|
Clark
|
Legislative District:
|
|
17
|
Congressional District 2022:
|
|
03
|
Sections:
|
|
47
|
Township:
|
|
T01NR03E
|
Coordinates:
|
|
45.58926847 -122.39155930
|
|
|
Worksite Name | Scope of Work | Proposed Development Cost |
S. Lacamas Creek (3rd Ave) Trailhead (#1)
|
Architectural & Engineering (A&E), Construct / install restroom, General site preparation, Install lighting (general security), Install power utilities, Install sewage system, Install signs/kiosk, Install site furnishings, Install stormwater system, Install water system, Landscaping improvements, Obtain permits, Trailhead Development
|
$1,154,837
|
| Total | $1,154,837 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
S. Lacamas Creek (3rd Ave) Trailhead (#1)
|
|
Property 1 - S. Lacamas Creek (3rd Ave) Trailhead
|
Local Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Proposed |
Restoration Metrics (rolled up from Worksite level) |
Buildings and Structures |
Construct / install restroom |
|
Number of restrooms
|
New: 1, Renov: 0
|
General Site Improvements |
Landscaping improvements |
|
Acres of landscaped area
|
0.11
|
Site Preparation |
General site preparation |
|
Acres of site preparation
|
0.75
|
Trailheads |
Trailhead Development |
|
Number of parking stalls - ADA
|
1
|
|
Number of parking stalls - Standard vehicle
|
24
|
General Site Improvements |
Install signs/kiosk |
|
Enter the number of signs / kiosks - Other signs
|
5
|
|
Enter the number of signs / kiosks - Permanent entrance signs
|
1
|
Permit Type | Applied Date | Received Date | Expiration Date | Permit Number |
Other Required Permits
|
02/06/2019
|
10/01/2019
|
10/01/2024
|
DR-19-04
|
Other Required Permits
|
02/06/2019
|
10/01/2019
|
10/01/2024
|
SPRV 19-02
|
SEPA
|
02/06/2019
|
10/01/2019
|
10/01/2024
|
SEPA 19-08
|
Shoreline Permit
|
02/06/2019
|
10/01/2019
|
10/01/2024
|
SHOR 19-01
|
Nationwide Permit
|
|
07/30/2019
|
03/18/2023
|
NWS-2018-907
|
Building Permit
|
|
|
|
|
Other Required Permits
|
|
|
|
|
Hydraulics Project Approval [HPA]
|
|
|
|
|
Milestone Name | Target Date | Description |
Applied for Permits
|
01/20/2019
|
File # SHOR19-01
|
SEPA/NEPA Completed
|
04/11/2019
|
USACE No. NWS-2018-0907
|
Project Start
|
07/10/2023
|
|
Design Initiated
|
08/31/2023
|
|
60% Plans to RCO
|
09/30/2023
|
|
All Bid Docs/Plans to RCO
|
11/30/2023
|
|
Cultural Resources Complete
|
12/31/2023
|
IDP Required
; see Special Condition
|
RCO Notice to Proceed
|
02/01/2024
|
|
Bid Awarded/Contractor Hired
|
02/05/2024
|
|
Construction Started
|
02/29/2024
|
|
Progress Report Due
|
03/01/2024
|
|
Annual Project Billing Due
|
07/31/2024
|
|
Progress Report Due
|
07/31/2024
|
|
50% Construction Complete
|
11/30/2024
|
|
RCO Interim Inspection
|
12/06/2024
|
|
Progress Report Due
|
01/31/2025
|
|
90% Construction Complete
|
05/31/2025
|
|
Funding Acknowl Sign Posted
|
07/31/2025
|
|
Construction Complete
|
07/31/2025
|
|
Progress Report Due
|
07/31/2025
|
|
Annual Project Billing Due
|
07/31/2025
|
|
RCO Final Inspection
|
10/03/2025
|
|
Final Billing Due
|
11/05/2025
|
|
Final Report Due
|
11/10/2025
|
|
Agreement End Date
|
12/31/2025
|
|
NOTE: This data is subject to change.